Estimate templates
Roof replacement estimate template
A roof replacement estimate covers the tear-off, the new roof system from the deck up, the flashing, the disposal bin and the labor. This template lists every line with its quantity and unit and leaves the prices to your own rates and suppliers.
Updated November 18, 2026
Template jobRoof replacementExample
“Tear off one layer and re-roof about 2,000 sq ft of roof with architectural shingles”
Change the sizes to your job. The line items below stay the same.
What goes in a roof replacement estimate
Roofers measure in squares (one square is 100 sq ft, a little over 9 m²). Measure the roof itself, not the floor area of the house.
| Line item | Quantity | Unit |
|---|---|---|
| Tear off the old shingles | roof area, for each layer | squares |
| Disposal bin | 1 | bin |
| Architectural shingles | roof area plus 10 to 15% waste | bundles |
| Starter strip | length of eaves and rakes | bundles |
| Hip and ridge cap | length of hips and ridges | bundles |
| Ice and water shield | eaves and valleys | rolls |
| Synthetic underlayment | rest of the roof | rolls |
| Drip edge | length of eaves and rakes | pieces |
| Pipe, wall and chimney flashing | count each one | each |
| Roof vents or ridge vent | count or length | each |
| Replacement roof deck sheets | as found | sheets |
| Labor to tear off, install and clean up | by crew size | hours |
What to check before you send it
- Count the layers. Lift a shingle at the edge. A second layer doubles the tear-off time and can need a second bin.
- Measure the slope. A steep roof has more surface than a low one over the same house, and it is slower and needs more safety gear.
- Price the deck sheets you cannot see. Give a price per sheet for rotten decking so nobody argues on tear-off day.
- List the flashing. Chimneys, skylights and walls take time. Say which flashing is new and which stays.
- Name the shingle. Write the product line and colour, and the maker's warranty that comes with it.
- Ask about a permit. Some towns want one for a re-roof.
Open it as a real quote
Press the button and this re-roof opens in Vorkeon as a job sentence. Put in your own roof area and the number of layers, and it works out the squares, bundles and rolls for you.
No sign-up. No card. The prices it shows are example rates until you add your own.
Questions
How do I work out roof area for an estimate?
Measure each roof plane and add them up, or multiply the footprint under the roof by a slope factor. Then divide by 100 to get squares if you work in square feet.
How much shingle waste should I add?
About 10% on a simple gable roof and 15% or more on a roof with hips, valleys and dormers, because of the cuts.
Should the disposal bin be its own line?
Yes. Bin prices vary a lot from town to town and by weight. A separate line lets you pass on the real cost and shows the customer where the money goes.